Monday, June 19th 3:00 PM
E.B. Newton Building
Business owners and residents are invited to attend to learn about the status of the Center Business Project.
Center Area Construction Updates for next week.
Crew 1
06/16 to 06/23 – The crew completed the main installation on Bartlett Rd and will complete the main installation on Adams St tomorrow. The crew will then move to Woodside Ave and start doing test holes from Pleasant Street to #72 Woodside Ave and reconnect to existing plastic main. The estimated time to complete the main installation on Woodside is Friday 06/23, barring any delays. The crew will then move to Williams St the following week to start test holes and prepping for main installation.
Crew 2
06/16 to 06/23 – The crew completed the stub installation on Woodside Ave @ Pleasant St. There are 4 remaining streets that the crew will install stubs for: Williams St going toward the odd side of pleasant street. Bartlett Rd, Cottage Park and Somerset Ave on the even side of the street, the stubs on the odd side of those streets are already completed.
No crews will be working on Saturday.