TWO WEEK LOOK-AHEAD
March 10, 2014 – March 21, 2014
The following are activities you can expect to see over the next two weeks for the Winthrop Beach Nourishment Project:
Crest Avenue – Winthrop
Site preparation
Excavate for new parking lot extension
Excavate for lighting system
Winthrop Beach
Install rodent control traps
Construct truck entrance at Dolphin Avenue
Install fence on seawall
Remove and reset revetment along seawall
Deliver armor stones
Reconstruct Groin #3
Demolition of Concrete at Groin #4
Saugus – Rumney Marsh
Install erosion control wattle
Install fence at Bristow Street
Construct truck entrance at Route 107
Strip and Screen soil
Clear and Grub (tree and brush removal)
Questions or concerns about the project should be directed to DCR Resident Engineer Steve Colometo, at the DCR trailer behind the DCR bathhouse on Winthrop Shore Drive, by visit or phone (617-539-4957) during regular business hours, Monday through Friday from 7 a.m. – 3:30 p.m. In case of an emergency, contact 911 or DCR’s 24/7 emergency hotline at the Massachusetts Emergency Management Agency at 508-820-1428.
Join us on Twitter @MassDCR – Visit http://mass.gov/dcr